NEW QUESTION # 10
Activity 1001 started on the scheduled date but has slipped 10 days. Activity 10002 will slip 35 days. All remaining activities retain their original duration. What is the revised completion date?
- A. 03-20-04
- B. 03-11-04
- C. 03-21-04
- D. 02-19-04
Answer: B
NEW QUESTION # 11
Using the normal schedule, given Activity 3001 and the relationship with Activity 4001. what is indicated?
- A. These activities are partially concurrent, with Activity 4001 starting 15 days after the start of Activity 3001
- B. The activities are independent, with Activity 4001 starting 15 days earlier than the start of Activity 5001
- C. These activities are sequential, with Activity 4001 starting 15 days earlier than the start of Activity 3001.
Answer: C
NEW QUESTION # 12
What is the remaining work duration of Active D?
- A. 8.
- B. 4.
- C. 3.
- D. 0
Answer: B
NEW QUESTION # 13
For activity 11001. why would the crashed direct cost be greater than the direct cost of the normal schedule?
- A. Management bonuses for early completion were included in this activity
- B. Some costs resulting from the crashed efforts were forgotten in previous activities
- C. Generally, more equipment is used for a crashed project; therefore, it costs more to demobilize
- D. Additional extended overhead is also being shown in this activity
Answer: C
NEW QUESTION # 14
At the end of month one, did the delay to the parking structure foundation delay the project?
- A. Yes, by 9 calendar days.
- B. Yes, by 4 calendar days.
- C. NO.
- D. Yes, by 14 calendar days.
Answer: B
NEW QUESTION # 15
What portion of Activity B is on the critical path?
- A. Last half of the activity
- B. First half of the activity
- C. The whole activity
- D. None of it
Answer: D
NEW QUESTION # 16
Which of the following will always describe the critical path? The path with
- A. Negative float.
- B. The shortest duration and negative float.
- C. Zero float.
- D. The longest duration through the network.
Answer: C
NEW QUESTION # 17
Identify the late finish to develop plans and specs.
- A. 8 months.
- B. 7 months.
- C. 9 months.
- D. 10 months.
Answer: C
NEW QUESTION # 18
These are the activities on the critical path:
- A. A, B, F, & J
- B. A, D, & I.
- C. A, C, E, & H.
- D. A, B, G, & H.
Answer: D
NEW QUESTION # 19
The work breakdown structure is used to organize
- A. The smallest defined work packet
- B. The chart of accounts
- C. Similar activity coding of schedule activities
- D. "Smart activity ID codes" representing similar items of scheduled work
Answer: A
NEW QUESTION # 20
Using the normal schedule, what is the early finish date and total float of Activity 10002?
- A. 21 Dec 2023. and 4 days of total float
- B. 17 Dec 2023. and 4 days of total float
- C. 24 Nov 2023. and 24 days of tree float
- D. 24 Dec 2023. and 24 days of tree float
Answer: A
NEW QUESTION # 21
Midway through the project you received an executed change order for this project, adding thirty-three days to the contract for weather delays. In its simplest form, how would your next project update display the changed condition?
- A. After Activity 1000, add a new Activity 1050 with a start-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-finish relationship to the final activity of the project.
- B. After Activity 1001, add a new Activity 1011 with a finish-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-start relationship to the final activity of the project.
- C. After Activity 1000, add a new Activity 1010 with a finish-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-start relationship to the final activity of the project.
Answer: B
NEW QUESTION # 22
A driving relationship is _____________________.
- A. A critical relationship.
- B. The link between two related activities.
- C. A finish-to-start relationship.
- D. The link between a predecessor and the activity whose dates it controls.
Answer: D
NEW QUESTION # 23
Which activity is drawn in the incorrect position?
- A. Activity E.
- B. Activity G.
- C. Activity C.
- D. Activity D.
Answer: C
NEW QUESTION # 24
What is the workweek period for this project?
- A. Monday through Friday
- B. Sunday through Friday
- C. Sunday through Saturday
- D. Monday through Saturday
Answer: C
NEW QUESTION # 25
Assuming a total of 30 lifts per crane per day, what is the maximum number of lifts that could be accomplished using 3 small tower cranes over a 5-day period?
- A. 150 lifts
- B. 450 lifts
- C. 45 lifts
- D. 300 lifts
Answer: B
NEW QUESTION # 26
Using a 1.75 cubic yard [1.34 cubic meter] bucket, how many lifts does it take to pour each 2.000-cubic foot [56.64 cubic meter] column?
- A. 42 lifts
- B. 133 lifts
- C. 60 lifts
- D. 30 lifts
Answer: D
NEW QUESTION # 27
How much Total Float does drafting the product manual have?
- A. 5 workdays.
- B. 0 workdays.
- C. 15 workdays.
- D. 10 workdays.
Answer: D
NEW QUESTION # 28
Prior to the beginning work on Activity 6001, the scope is changed by executed change order to increase the activity duration by thirty days and rock fill by 100.000 cubic meters If the project has progressed as scheduled up to the point of the executed change order, what activities would be changed on the next project update?
- A. 1001 and 6001
- B. 9001 and 6002 and 6002
- C. 1000. 1001. and 6001
- D. 1000 and 6001
Answer: B
NEW QUESTION # 29
Why does activity 1001 have two successor activities?
- A. Because the duration of activities 2001, 2002 and 200.f require two successors
- B. Because the late finish of 1001 and the late start of 7001 require two successors
- C. Because there are two defined logic paths for the work
- D. Because the problem could not effectively work with only one successor
Answer: C
NEW QUESTION # 30
Determine the correct formula and date for the late finish for Activity 9004.
- A. LS.10002^ Lag.7 + i day -> 11-20-03.
- B. LS.10002 - Lag.7 - l day -> 11-20-03.
- C. LS.10002 - 1 day -> 11-27-03.
- D. LS.10002 + 1 day -> 11-29-03.
Answer: A
NEW QUESTION # 31
Which of the following documents is most likely to be of the LEAST value to a planner/scheduler when planning a contractor's baseline critical path schedule for the construction of a large high-clearance bridge located very near an airport? The contractor has been awarded the contract.
- A. The project plans and specifications
- B. The regulations published by the government aviation agency
- C. The government's report on future high-clearance bridge projects
- D. The project geotechnical report
Answer: B
NEW QUESTION # 32
Using the crashed schedule, if you start Activity 2002 on 12 August 2021. what is the finish date for Activity 2002?
- A. 09 Sep 2021
- B. 19 Sep 2021
- C. 27 Aug 2021
- D. 08 Sep 2021
Answer: B