NEW QUESTION 38
Which of the following project planning situations is the most frequent contributor to cost overruns?

  • A. Inappropriate definition of work breakdown structure
  • B. Inadequate definition of scope at the estimate (budget) stage
  • C. lack of detailed planning for operational start-up
  • D. Insufficient planning for change management

Answer: B

 

NEW QUESTION 39
In its simplest form, what is the main drawback of critical path method scheduling?

  • A. It requires a backward pass to calculate late dates.
  • B. It assumes that resources are unlimited.
  • C. It allows for Precedence Diagramming Method to be used in place of Arrow Diagramming Method.
  • D. It doesn't account for interdependent between activities.

Answer: B

 

NEW QUESTION 40
Using the "normal" schedule, what is the early finish date of activity 10002 and its total float?

  • A. 12-17-03 and 4 days of float
  • B. 12-18-03 and 25 days of float
  • C. 12-18-03 and 4 days of float
  • D. 12-27-03 and 24 days of float

Answer: A

 

NEW QUESTION 41
Activity C is a

  • A. Continuous activity.
  • B. Milestone.
  • C. Contentious activity.
  • D. 1-day activity.

Answer: B

 

NEW QUESTION 42
What is the actual duration as of the status date or data date of Activity B?

  • A. 7.
  • B. 3.
  • C. 0.
  • D. 4.

Answer: B

 

NEW QUESTION 43
What is a key first step in developing a critical path method schedule?

  • A. Drawing the logic diagram.
  • B. Drawing a bar chart of the key phrases of the work.
  • C. Setting out the resource to be used and its limitations.
  • D. Defining the execution plan to meet the required scope of work.

Answer: A

 

NEW QUESTION 44
Which of the following types of delay will NOT result in a time extension and additional compensation for a contractor?

  • A. Compensable delay
  • B. Excusable delay
  • C. Non-compensable delay
  • D. Non-excusable delay

Answer: C

 

NEW QUESTION 45
Theoretically construct a summary activity for activities 6001 through 6003. Identify the governing predecessor and successor activities for the hammock:

  • A. Predecessor is activity 5001, successor is activity 8001
  • B. Predecessor is activity 5001, successor is activity 8002
  • C. Predecessor is activity 4001, successor is activity 8001
  • D. Predecessor is activity 9001, successor is activity 9002

Answer: A

 

NEW QUESTION 46
During proofing of the product manual, a problem was discovered requiring 15 days additional time to effect a correction. How can the date of availability be maintained?

  • A. Expedite packaging by 5 days.
  • B. Delay manufacturing by 5 days.
  • C. Delay product release by 5 days.
  • D. Expedite printing by 5 days.

Answer: C

 

NEW QUESTION 47
Which of the following documents is most likely to be of the LEAST value to a planner/scheduler when planning a contractor's baseline critical path schedule for the construction of a large high-clearance bridge located very near an airport? The contractor has been awarded the contract.

  • A. The regulations published by the government aviation agency
  • B. The project geotechnical report
  • C. The government's report on future high-clearance bridge projects
  • D. The project plans and specifications

Answer: C

 

NEW QUESTION 48
The activity with the most total float is:

  • A. Activity D.
  • B. Activity I.
  • C. Activity C.
  • D. Activity F.

Answer: B

 

NEW QUESTION 49
A driving relationship is _____________________.

  • A. A finish-to-start relationship.
  • B. A critical relationship.
  • C. The link between two related activities.
  • D. The link between a predecessor and the activity whose dates it controls.

Answer: D

 

NEW QUESTION 50
For the late finish for Activity 11001, select the most appropriate response for transitioning from the forward pass.

  • A. LS.11001 + 25 days.
  • B. EF.11001.
  • C. 02-19-04.
  • D. EF.11001 + 1 day.

Answer: C

 

NEW QUESTION 51
What activities are concurrent to Activity 2001 in the "normal" schedule?

  • A. 1000.
  • B. 1001.
  • C. 7001.
  • D. 2003.

Answer: C

 

NEW QUESTION 52
Determine the driving activity for Activity 10001.

  • A. There is no driving activity for Activity 10001 in the backward pass.
  • B. Activity 10002.
  • C. Activity 11001.
  • D. Activity 9005.

Answer: B

 

NEW QUESTION 53
Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?

  • A. Front end loading.
  • B. Multiple calendars.
  • C. Preferential logic.
  • D. Start and finish constraints.

Answer: A

 

NEW QUESTION 54
Under which circumstance should one perform resource-leveling calculations?

  • A. When the schedule is resource-loaded.
  • B. When the contract contains a provision for float-banking.
  • C. When you believe that known resource limitations may override schedule logic.
  • D. Never, unless required by the contract.

Answer: C

 

NEW QUESTION 55
Which of the following phases does NOT describe the commonly accepted construction life cycle?

  • A. Claims and disputes phase.
  • B. Turnover and start-up phase.
  • C. Planning and design phase.
  • D. Installation phase.

Answer: C

 

NEW QUESTION 56
If a detailed estimate is NOT available to assist in the formulation of activity durations but unit quantities have been identified, what information can be utilized to estimate work package/activity durations?

  • A. Historical production rates
  • B. Black-Scholes model
  • C. Time impact analysis
  • D. The Eichleay formula

Answer: A

 

NEW QUESTION 57
What is the relationship depicted between Activity G and Activity H?

  • A. Finish-to-finish.
  • B. Start-to-start.
  • C. Finish-to-start.
  • D. You cannot tell with the supplied information.

Answer: B

 

NEW QUESTION 58
When resource leveling craft labor for a critical path schedule, the scheduler

  • A. Can depend on the results of the resource leveling operation to reflect a useful realignment of all schedule activities without 'further analysis.
  • B. Need only consider the non-union crafts persons.
  • C. Need not consider its effects, as it is a theoretical concept with limited application to construction projects.
  • D. Must consider breaks in continuity of work for subcontractors, thereby possibly incurring additional subcontractor mobilization and demobilization costs.

Answer: A

 

NEW QUESTION 59
Of the following update procedures, which is the least important in achieving an accurate forecast for completion of a construction schedule?

  • A. Estimating remaining durations of activities.
  • B. The correct recording of actual start dates.
  • C. Entering the time impacts of delays and change orders.
  • D. Making "downstream" logic revisions as required.

Answer: D

 

NEW QUESTION 60
Determine the correct formula and date for the late start for Activity 9001.

  • A. LF.9001 Dur.9001 -> 11-20-02.
  • B. The early finish is required in order to determine the answer.
  • C. There is insufficient data provided to calculate the answer.
  • D. LS.6001 Dur.6001 -> 11-20-02.

Answer: A

 

NEW QUESTION 61
Each column must be poured in one day. Each column requires 2,000 cubic feet of concrete. The lift bucket has a capacity of 40 cubic feet. How many lifts will be required per column pour?

  • A. 20 lifts
  • B. 80 lifts
  • C. 50 lifts
  • D. 5 lifts

Answer: C

 

NEW QUESTION 62
What is the result of a forward pass calculation?

  • A. Critical path
  • B. Value of free float for individual activities
  • C. Early start and early finish date for individual activities
  • D. Value of total float for individual activities

Answer: C

 

NEW QUESTION 63
......