Pass PRINCE2 PRINCE2-Foundation Actual Free Exam Q&As Updated Dump Feb 27, 2024
Latest PRINCE2-Foundation Actual Free Exam Updated 340 Questions
PRINCE2 Foundation certification exam is suitable for individuals who are new to project management, as well as those who are experienced project managers. PRINCE2 Foundation written Exam certification is also beneficial for those who want to work in an organization that uses PRINCE2 methodology. PRINCE2 Foundation written Exam certification provides individuals with the knowledge and skills required to manage projects effectively, and it helps them demonstrate their proficiency in PRINCE2 methodology.
PRINCE2 PRINCE2-Foundation (PRINCE2 Foundation written) Exam is a globally recognized certification that is designed to equip individuals with the knowledge and skills required to effectively manage projects using the PRINCE2 methodology. PRINCE2 (an acronym for PRojects IN Controlled Environments) is a project management methodology that provides a framework for managing projects effectively, efficiently, and with a focus on delivering value to the organization. The PRINCE2 methodology is widely used in both the public and private sectors, and the PRINCE2-Foundation Exam is an essential certification for anyone looking to work in project management.
NEW QUESTION # 27
During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin?
- A. End Stage Report
- B. Team Plan
- C. Project Plan
- D. Work Package
Answer: C
NEW QUESTION # 28
What product defines the reporting requirements between the Project Manager and Team Manager?
- A. Product Description
- B. Work Package
- C. Project Brief
- D. Team Plan
Answer: B
NEW QUESTION # 29
What information should be recorded in the quality register?
- A. Planned activities to determine whether the products are fit for purpose
- B. Off-specifications that will occur during the project
- C. Potential threats to the project's objectives and how they will be managed
- D. Lessons that the project will capture and use during the project
Answer: D
Explanation:
Section: Volume B
Explanation/Reference:
Reference https://mplaza.pm/prince2-quality-register-template/
NEW QUESTION # 30
What is the project manager role responsible for?
- A. Approving the completion of each management stage
- B. Defining the project-level tolerances
- C. Ensuring that the project produces the required products
- D. Verifying that the project gives value for money
Answer: C
Explanation:
Explanation/Reference:
Reference http://prince2.wiki/Project_Manager
NEW QUESTION # 31
Which of the following is NOT part of quality planning?
- A. Define quality responsibilities
- B. Gain acceptance of the project product
- C. Set quality tolerances
- D. Agree acceptance criteria
Answer: B
NEW QUESTION # 32
What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?
- A. Highlight Report
- B. Checkpoint Report
- C. Configuration Item Record
- D. Quality Register
Answer: B
Explanation:
Section: Volume B
NEW QUESTION # 33
If a project's benefit tolerance is forecast to be exceeded, to whom should this be escalated to for a decision?
- A. Executive
- B. Senior User
- C. Corporate/programme management
- D. Senior Supplier
Answer: C
NEW QUESTION # 34
Which is an objective of the 'managing a product delivery' process?
- A. To assess whether the stage products have been approved
- B. To deliver the planned specialist products within tolerance
- C. To request authorization to start the next stage
- D. To ensure the business case is regularly reviewed
Answer: B
Explanation:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Managing_Product_Delivery#Objective
NEW QUESTION # 35
According to PRINCE2, why might there be more than one business case for a project?
- A. The project may be in a commercial environment with a number of suppliers
- B. There may be more than one management stage in the project
- C. There may be more than one work package being delivered in the project
- D. The project may be in a programme environment
Answer: A
Explanation:
Explanation/Reference:
Reference https://www.prince2primer.com/prince2-practitioner-questions-answers-business-case/
NEW QUESTION # 36
Which of the following statements about lines of authority and reporting are true?
1, The Project Manager has day-to-day control for a management stage within the limits laid,
2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager down by the Project Board.
- A. Only 1 is true
- B. Only 2 is true
- C. Both 1 and 2 are true
- D. Neither 1 or 2 are true
Answer: C
NEW QUESTION # 37
Which is a purpose of a lessons log?
- A. To escalate lessons to the project board
- B. To record any lessons that are raised in checkpoint reports
- C. To document that corrective action is being taken
- D. To raise improvements with project assurance
Answer: B
Explanation:
Explanation/Reference:
Reference https://mplaza.pm/prince2-lessons-log-template/
NEW QUESTION # 38
What action is taken as part of the 'controlling a stage' process?
1. Create an exception plan
2. Authorize work to be done
3. Take corrective action
4. Obtain approvals for completed products
- A. 1 and 4
- B. 3 and 4
- C. 1 and 2
- D. 2 and 3
Answer: D
Explanation:
Explanation
Reference
https://www.greycampus.com/opencampus/prince-2-foundation/introduction-on-controlling-a-stage-process-in-p
NEW QUESTION # 39
Identify the missing word in the following sentence, A purpose of the [?] theme is to control any unacceptable deviations from the project's objectives.
- A. Plans
- B. Risk
- C. Change
- D. Progress
Answer: D
NEW QUESTION # 40
What is an off-specification?
- A. A type of issue
- B. A new requirement
- C. A major risk
- D. A quality tolerance
Answer: A
NEW QUESTION # 41
Which is an objective of the Starting up a Project process?
- A. Agree how issues and changes will be identified, assessed and controlled
- B. Agree how the project will be monitored and controlled after initiation
- C. Authorize the Project Manager to proceed with the initiation stage
- D. Identify who will be responsible for creating the Project Plan
Answer: D
NEW QUESTION # 42
During the 'initiating a project' process, who specifies the required level of management control?
- A. Project board
- B. Project assurance
- C. Corporate, programme management or customer
- D. Project manager
Answer: A
NEW QUESTION # 43
How should the Team Manager report that tolerances are forecast to be exceeded?
- A. Create an Exception Report
- B. Create a Highlight Report
- C. Raise an issue
- D. Grant a concession
Answer: C
Explanation:
Section: Volume B
NEW QUESTION # 44
Which is an objective of the Initiating a Project process?
- A. Request authority from corporate management to deliver the project
- B. Prepare the plans for the subsequent stages
- C. Develop the corporate quality management system as part of the Project Initiation Documentation
- D. Summarize how the organization's project management method will be tailored for the project
Answer: D
NEW QUESTION # 45
Which of the following take place before the initiation of a project?
1.Appoint the Executive
2.Capture requirements
3.Develop the Project Brief
4.Develop the detailed Business Case
- A. 1, 2, 4
- B. 1, 2, 3
- C. 2, 3, 4
- D. 1, 3, 4
Answer: B
NEW QUESTION # 46
Which is the Issue Register NOT used for?
- A. Record any problems identified when authorizing a Work Package
- B. Record information about a deviation in stage tolerance
- C. Capture any threats or opportunities that might have an impact on a stage
- D. Capture external events that are impacting a stage
Answer: C
Explanation:
Section: Volume A
NEW QUESTION # 47
Which is a purpose of the 'initiating a project' process?
- A. To identify the number of work packages required
- B. To decide on the project approach
- C. To decide if it is worthwhile to initiate a project
- D. To establish solid foundations for a project
Answer: D
Explanation:
Reference http://prince2.wiki/Initiating_a_Project#Objective
NEW QUESTION # 48
......