NEW QUESTION 40
Your customer wants to use requirements grouping in SAP Project System. What are the prerequisites for requirements grouping of materials? Note: There are 2 correct Answers to this question.
- A. The procurement type of the material must be internal.
- B. The exact lot size procedure must be used.
- C. The materials must allow sales order or project stock.
- D. An MRP group must be assigned.
Answer: C,D
NEW QUESTION 41
Which of the following business processes do NOT lead to the booking of actual costs to an object?
Note: There are 2 correct Answers to this question.
- A. Goods receipt of a non-stock item
- B. Goods receipt into unvaluated project stock
- C. Goods receipt into valuated project stock
- D. Recording of external services in the service entry sheet
Answer: B,D
NEW QUESTION 42
Which object is relevant in assembly processing to create an assembly order for the SD document?
- A. Item category
- B. Control key
- C. Requirement class
- D. Project profile
Answer: C
NEW QUESTION 43
Where do you control whether a project stock is managed as valuated or non-valuated project stock?
- A. In the project definition
- B. In the material master
- C. In the network activity
- D. In the WBS element
Answer: A
NEW QUESTION 44
Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component?
- A. Set up the requirement date aligned with the activity finish date and an offset of 15 days.
- B. Set up the requirement date manually as February 5.
- C. Set up the requirement date aligned with the activity start date and an offset of 5 days.
- D. Set up the requirement date aligned with the activity start date and a negative offset of 5 days.
Answer: C
NEW QUESTION 45
Which of the following is visible in the project planning board? Note: There are 2 correct Answers to this question.
- A. Maintenance orders assigned to an activity
- B. Project-relevant purchase orders
- C. Production orders assigned to WBS elements
- D. Capacity requirements
Answer: A,D
NEW QUESTION 46
Budgeting is implemented for projects. The budget has been adjusted several times. What standard report type provides an overview of adjustments on the budget?
- A. Structure overview for budgets
- B. Cost element report on budget updates
- C. Line item report for budgets
- D. Hierarchical report on budget updates
Answer: C
NEW QUESTION 47
You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? Note: There are 2 correct Answers to this question.
- A. Shift activities backward or forward on the time axis where more capacities are available.
- B. Maintain subordinate internal activity elements assigned to other work centers.
- C. Increase the capacities of the work center in the project planning board.
- D. Trigger automatic capacity leveling inside the project planning board.
Answer: A,D
NEW QUESTION 48
How can you grant individual authorization for WBS elements and networks?
- A. Define a user status to lock the business transaction Update Project.
- B. Set the system status to "Lock Master Data".
- C. Activate access control lists (ACL) for the user master record.
- D. Activate access control lists (ACL) for the project profile and the network profile.
Answer: D
NEW QUESTION 49
Which of the following factors influence the scheduling of internal processing activities? Note: There are
3 correct Answers to this question.
- A. Whether the work for the internal activity is greater than its duration
- B. The unit (for example, hour, day) of the field Normal Duration field of the activity
- C. The relationships between activity elements
- D. The factory calendar in the work center used for the internal processing activity
- E. An activated Scheduling indicator in the control key of the internal processing activity
Answer: C,D,E
NEW QUESTION 50
A component is assigned to a network activity. What are the prerequisites to generate project stock reservations? Note: There are 3 correct Answers to this question.
- A. The network is assigned to a sales order item.
- B. The network activity is assigned to a WBS element.
- C. The Project Stock indicator is set in the project definition (non-valuated or valuated).
- D. The material master of the component must permit project stock management.
- E. A procurement indicator must be assigned to the activity.
Answer: C,D,E
NEW QUESTION 51
How can you update the degree of processing for an activity?
- A. By using results analysis
- B. By confirming the activity
- C. By changing the activity
- D. By scheduling the activity
Answer: B
NEW QUESTION 52
Which planning method can prevent further rescheduling of activities?
- A. Capacity requirements activation
- B. Partial confirmation of activities
- C. Capacity leveling
- D. Workforce planning
Answer: A
NEW QUESTION 53
Which report can use user-specific layouts?
- A. Cost element report
- B. Line item report
- C. Hierarchical report
- D. Enhanced individual overview
Answer: B
NEW QUESTION 54
The basic dates of subordinate WBS elements should be extrapolated without taking into account the basic dates of higher-level WBS elements. What planning method for basic dates do you use?
- A. Top-down
- B. Bottom-up
- C. Strict bottom-up
- D. Free planning
Answer: B
NEW QUESTION 55
What functions are available for period end closing in SAP Project System? Note: There are 3 correct Answers to this question.
- A. Progress analysis
- B. Results analysis
- C. Settlement
- D. Milestone trend analysis
- E. Confirmations
Answer: A,B,C
NEW QUESTION 56
Where can you assign the user status profile for WBS elements? Note: There are 3 correct Answers to this question.
- A. In the project version
- B. In the project definition of a standard WBS
- C. In the project type
- D. In the operative WBS element
- E. In the project profile
Answer: B,D,E
NEW QUESTION 57
Which of the following actions can transfer actual costs for external processing? Note: There are 2 correct Answers to this question.
- A. Saving a goods receipt
- B. Saving a supplier invoice
- C. Saving a service entry sheet
- D. Saving a purchase order
Answer: A,C
NEW QUESTION 58
You want to set up the field selection of the Cross-Application Time Sheet (CATS) in Customizing. Which influencing field do you use?
- A. Network profile
- B. Data entry profile
- C. Network type
- D. Project profile
Answer: B
NEW QUESTION 59
Where can you define a network as "header-account-assigned" or "activity-account-assigned"?
- A. Network profile
- B. Network type
- C. Project profile
- D. Parameters for the network type
Answer: D
NEW QUESTION 60
......